Sonotube & Post-Hole Concrete Calculator — 50/60/80-lb Bag Counts, Cubic Yards & Wood Post Displacement.
Calculate exact 50-lb, 60-lb, or 80-lb concrete bags, cubic yards, and mixing water for cylindrical Sonotube deck footings or fence post holes—automatically subtracting 4×4 or 6×6 post displacement.
80-lb Concrete Bags
31 bags
Includes 10% over-dig buffer
Total Concrete Volume
0.67 yd³
18.1 ft³ (2.75 ft³/hole)
Est. Material Cost
$209
At $6.75 / bag
Mixing Water Needed
~23.3 gal
Keep mix stiff — avoid soupy pours
CONCRETE FOOTING MATH
Frequently Asked Questions
How many 80-lb bags of concrete fill a 12-inch × 4-foot Sonotube?
A 12-inch diameter, 48-inch deep cylinder holds 3.14 cubic feet of concrete. Because one 80-lb bag yields 0.60 cubic feet, you need roughly 5.2 bags—so plan on 6 bags per footing with a 10% spillage allowance.
How wide should a fence post hole be for a 4×4 post?
Dig the hole about 3 times the width of the post (roughly 10 to 12 inches wide for a 4×4) and at least 1/3 of the post’s above-ground height deep, extending below your local frost line.